Commission Decision of 13 June 2008 on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document number C(2008) 2625) (Text with EEA relevance) (2008/477/EC)
Grade B
mapped from publisher markup. A grade says how a document's structure was obtained, not how reliable the law is.
Address https://gelex.eu/eli/EU/decision/2008/477@2008-06-13/en
Contents
- Preamble
- ANNEX
- ANNEX PARAMETERS REFERRED TO IN ARTICLE 2
- B. Table 1 Table 2 Table 3 Baseline requirements — Base Station out-of-block e.i.r.p. BEM Block specific requirements — Base Station in-block e.i.r.p. BEM Block specific requirements — base station out-of-block e.i.r.p. BEM
- C. Table 4 Block specific requirements — base station in-block e.i.r.p. BEM for restricted block
- D. Table 5 Block specific requirements — base station out-of-block e.i.r.p. BEM for restricted block with additional restrictions on antenna placement
- E. Table 6 In-block power limits for terminal stations
THE COMMISSION OF THE EUROPEAN COMMUNITIES,
Having regard to the Treaty establishing the European Community,
Having regard to Decision No 676/2002/EC of the European Parliament and of the Council of 7 March 2002 on a regulatory framework for radio spectrum policy in the European Community (Radio Spectrum Decision), and in particular Article 4(3) thereof,
Whereas:
(1) The Commission has supported a more flexible use of spectrum in its Communication on Rapid access to spectrum for wireless electronic communications services through more flexibility, which, inter alia, addresses the 2500-2690 MHz band. Technological neutrality and service neutrality have been underlined by Member States in the Radio Spectrum Policy Group (RSPG) opinion on Wireless Access Policy for Electronic Communications Services (WAPECS) of 23 November 2005 as important policy goals to achieve a more flexible use of spectrum. Moreover, according to this opinion, these policy goals should not be introduced abruptly, but in a gradual manner to avoid disruption of the market.
(2) The designation of the 2500-2690 MHz band for systems capable of providing electronic communications services is an important element addressing the convergence of the mobile, fixed and broadcasting sectors and reflecting technical innovation. The services provided in this frequency band should mainly target end-user access to broadband communications.
(3) It is expected that the wireless broadband electronic communications services for which the 2500-2690 MHz band is to be designated will to a large extent be pan-European in the sense that users of such electronic communications services in one Member State could also gain access to equivalent services in any other Member State.
(4) Pursuant to Article 4(2) of Decision No 676/2002/EC, on 5 July 2006 the Commission gave a mandate to the European Conference of Postal and Telecommunications Administrations (hereinafter the CEPT) to develop least restrictive technical conditions for frequency bands addressed in the context of WAPECS.
(5) In response to that mandate, the CEPT has issued a report (CEPT Report 19) on least restrictive technical conditions for frequency bands addressed in the context of WAPECS. This report contains technical conditions and guidance for the application of least restrictive conditions to base stations and terminal stations operating in the 2500-2690 MHz band, which are appropriate to manage the risk of harmful interference within as well as outside of national territories, without requiring that any type of particular technology is used, based on optimised parameters for the most likely use of the band.
(6) In accordance with CEPT Report 19 this Decision introduces the concept of Block Edge Masks (BEM), which are technical parameters that apply to the entire block of spectrum of a specific user, irrespective of the number of channels occupied by the user's chosen technology. These masks are intended to form part of the authorisation conditions for spectrum usage. They cover both emissions within the block of spectrum (i.e. in-block power) as well as emissions outside the block (i.e. out-of-block emission). They are regulatory requirements aimed at managing the risk of harmful interference between neighbouring networks and are without prejudice to limits set in equipment standards under Directive 1999/5/EC of the European Parliament and of the Council of 9 March 1999 on radio equipment and telecommunications terminal equipment and the mutual recognition of their conformity (the R&TTE Directive).
(7) The designation and making available of the 2500-2690 MHz band in accordance with the results of the mandate to CEPT recognises the fact that there are other existing applications. Appropriate sharing criteria for coexistence between some systems have been developed in the Electronic Communications Committee's ECC Report 45. For other systems and services appropriate sharing criteria for coexistence may be based on national considerations.
(8) To achieve compatibility a separation of 5 MHz is needed between the edges of spectrum blocks used for unrestricted TDD (time division duplex) and FDD operation (frequency division duplex) or in the case of two unsynchronised networks operating in TDD mode. Such separation should be achieved by either leaving these 5 MHz blocks unused as guard blocks; or through usage that complies with parameters of the restricted BEM when adjacent to an FDD (uplink) or between two TDD blocks; or through usage that complies with parameters of either restricted or unrestricted BEMs when adjacent to an FDD (downlink) block. Any usage of a 5 MHz guard block is subject to an increased risk of interference.
(9) The results of the mandate to the CEPT should be made applicable in the Community and implemented by the Member States without delay given the increasing requirements identified in studies at European and global levels for terrestrial electronic communications services providing broadband communications.
(10) Harmonisation under this Decision should not exclude the possibility for a Member State to apply, where justified, transitional periods that could include radio spectrum sharing arrangements, pursuant to Article 4(5) of the Radio Spectrum Decision.
(11) In order to ensure effective use of the 2500-2690 MHz band also in the longer term, administrations should continue with studies that may increase efficiency and innovative use. Such studies should be taken into account when considering a review of this Decision.
(12) The measures provided for in this Decision are in accordance with the opinion of the Radio Spectrum Committee,
HAS ADOPTED THIS DECISION:
Article 1
This Decision aims at harmonising the conditions for the availability and efficient use of the 2500-2690 MHz band for terrestrial systems capable of providing electronic communications services in the Community.
Article 2
1. No later than six months after entry into force of this Decision Member States shall designate and subsequently make available, on a non-exclusive basis, the 2500-2690 MHz band for terrestrial systems capable of providing electronic communications services, in compliance with the parameters set out in the Annex to this Decision.
2. By way of derogation from paragraph 1, Member States may request transitional periods that may include radio spectrum sharing arrangements, pursuant to Article 4(5) of Decision No 676/2002/EC.
3. Member States shall ensure that systems referred to in paragraph 1 give appropriate protection to systems in adjacent bands.
Article 3
Member States shall keep the use of the 2500-2690 MHz band under scrutiny and report their findings to the Commission to allow regular and timely review of this Decision.
Article 4
This Decision is addressed to the Member States.
Done at Brussels, 13 June 2008. For the Commission Viviane Reding Member of the Commission
ANNEX
ANNEX PARAMETERS REFERRED TO IN ARTICLE 2
The following technical parameters called Block Edge Mask (BEM) shall be applied as an essential component of conditions necessary to ensure coexistence in the absence of bilateral or multilateral agreements between neighbouring networks, without precluding less stringent technical parameters if agreed among the operators of such networks. Member States should ensure that network operators are free to enter into bilateral or multilateral agreements to develop less stringent technical parameters and, if agreed among all affected parties, these less stringent technical parameters may be used. Equipment operating in this band may also make use of equivalent isotropically radiated power (e.i.r.p.) limits other than those set out below provided that appropriate mitigation techniques are applied which comply with Directive 1999/5/EC and which offer at least an equivalent level of protection to that provided by these technical parameters.
A.1.2.3. GENERAL PARAMETERS The assigned blocks shall be in multiple of 5,0 MHz. Within the band 2500–2690 MHz, the duplex spacing for FDD operation shall be 120 MHz with terminal station transmission (up link) located in the lower part of the band starting at 2500 MHz (extending to a maximum limit of 2570 MHz) and base station transmission (down link) located in the upper part of the band starting at 2620 MHz. The sub-band 2570–2620 MHz can be used by TDD or other usage modes complying with the BEMs in this Annex. Outside of the sub-band 2570–2620 MHz such usage can be decided at national level and shall be in equal parts in both the upper part of the band starting at 2690 MHz (extending downwards) and the lower part of the band starting at 2570 MHz (extending downwards).
B. Table 1 Table 2 Table 3 Baseline requirements — Base Station out-of-block e.i.r.p. BEM Block specific requirements — Base Station in-block e.i.r.p. BEM Block specific requirements — base station out-of-block e.i.r.p. BEM
UNRESTRICTED BEM FOR BASE STATIONS The BEM for an unrestricted spectrum block is built up by combining Tables 1, 2 and 3 in such a way that the limit for each frequency is given by the higher value out of the baseline requirements and the block specific requirements. Frequency range in which out-of-block emissions are received Maximum mean e.i.r.p. (integrated over a 1 MHz bandwidth) Frequencies allocated to FDD down link and ± 5 MHz outside the range of frequency blocks allocated to FDD down link. + 4 dBm/MHz Frequencies in the band 2500-2690 MHz not covered by the definition above. – 45 dBm/MHz NB: Member States can relax this limit to 68 dBm/5 MHz for specific deployments e.g. in areas of low population density provided that this does not significantly increase the risk of terminal station receiver blocking. Maximum in-block e.i.r.p. + 61 dBm/5 MHz Where: ΔF is the frequency offset from the relevant block edge (in MHz). Offset from relevant block edge Maximum mean e.i.r.p. Start of band (2500 MHz) to – 5 MHz (lower edge) Baseline requirement level – 5,0 to – 1,0 MHz (lower edge) + 4 dBm/MHz – 1,0 to – 0,2 MHz (lower edge) + 3 + 15(ΔF + 0,2) dBm/30 kHz – 0,2 to 0,0 MHz (lower edge) + 3 dBm/30 kHz 0,0 to + 0,2 MHz (upper edge) + 3 dBm/30 kHz + 0,2 to + 1,0 MHz (upper edge) + 3-15(ΔF – 0,2) dBm/30 kHz + 1,0 to + 5,0 MHz (upper edge) + 4 dBm/MHz + 5,0 MHz (upper edge) to end of band (2690 MHz) Baseline requirement level
C. Table 4 Block specific requirements — base station in-block e.i.r.p. BEM for restricted block
RESTRICTED BEM FOR BASE STATIONS The BEM for a restricted spectrum block is built up by combining Tables 1 and 4 in such a way that the limit for each frequency is given by the higher value out of the baseline requirements and the block specific requirements. Maximum in-block e.i.r.p. + 25 dBm/5 MHz
D. Table 5 Block specific requirements — base station out-of-block e.i.r.p. BEM for restricted block with additional restrictions on antenna placement
RESTRICTED BEM FOR BASE STATIONS WITH RESTRICTIONS ON ANTENNA PLACEMENT In cases where antennas are placed indoors or where the antenna height is below a certain height, a Member State may use alternative parameters in line with Table 5, provided that at geographical borders to other Member States Table 1 applies and that Table 4 remains valid nationwide. Where: ΔF is the frequency offset from the relevant block edge (in MHz). Offset from relevant block edge Maximum mean e.i.r.p. Start of band (2500 MHz) to – 5 MHz (lower edge) – 22 dBm/MHz – 5,0 to – 1,0 MHz (lower edge) – 18 dBm/MHz – 1,0 to – 0,2 MHz (lower edge) – 19 + 15(ΔF + 0,2) dBm/30 kHz – 0,2 to 0,0 MHz (lower edge) – 19 dBm/30 kHz 0,0 to + 0,2 MHz (upper edge) – 19 dBm/30 kHz + 0,2 to + 1,0 MHz (upper edge) – 19-15(ΔF - 0,2) dBm/30 kHz + 1,0 to + 5,0 MHz (upper edge) – 18 dBm/MHz + 5,0 MHz (upper edge) to end of band (2690 MHz) – 22 dBm/MHz
E. Table 6 In-block power limits for terminal stations
LIMITS FOR TERMINAL STATIONS NB: E.i.r.p. should be used for fixed or installed terminal stations and the TRP should be used for the mobile or nomadic terminal stations. TRP is a measure of how much power the antenna actually radiates. The TRP is defined as the integral of the power transmitted in different directions over the entire radiation sphere. Maximum mean power (including Automatic Transmitter Power Control (ATPC) range) Total radiated power (TRP) 31 dBm/5 MHz e.i.r.p. 35 dBm/5 MHz
Versions
Cited by
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
Having regard to Commission Decision 2008/477/EC of 13 June 2008 on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community, and in particular Article 2(2) thereof,
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
Decision 2008/477/EC provides that Member States are to designate and make available, on a non-exclusive basis, the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services, in accordance with the parameters set out in the Annex to that Decision.
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
The Netherlands has informed the Commission that, while authorisations have been granted for the use of the major part of the 2570 – 2620 MHz sub-band in accordance with Implementing Decision (EU) 2020/636, two limited sections of the band, namely the 2565-2570 MHz and 2685-2690 MHz lots, are still subject to two authorisations implementing time division duplex (TDD) instead of frequency division duplex (FDD) that were granted in 2010 pursuant to Decision 2008/477/EC and will expire in 2030.
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
In support of its request, the Netherlands has provided sufficient information and justification. By maintaining during the transitional period the two existing authorisations which are used for the provision of public mobile communications services, the Dutch authorities avoid interrupting the provision of mobile communications services by the holders of these two authorisations and avoid disrupting the present competition level playing field situation on the mobile communications market in The Netherlands. Moreover, the extensive usage restrictions attached to the use of the two correspondin
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
Moreover, the emission power limits attached to the use of that spectrum under the relevant authorisations are in line with the international coordination agreements concluded with the neighbouring Member States in order to ensure that no interference is created into those Member States. Consequently, the transitional period will not defer the implementation of Decision 2008/477/EC in neighbouring Member States.
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
For these reasons, the requested transitional period appears justified and proportionate and would not unduly defer implementation of Decision 2008/477/EC in the Netherlands or in the other Member States or create undue differences in the competitive or regulatory situation between Member States.
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
A transitional period is hereby granted to the Netherlands under Decision 2008/477/EC subject to the conditions laid down in that Decision.
- Commission Decision (EU) 2021/1038 of 23 June 2021 granting a transitional period to the Kingdom of the Netherlands pursuant to Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2500-2690 MHz frequency band (notified under document C(2021) 4433) (Only the Dutch text is authentic) Decision · Grade B
The Netherlands shall continue to ensure that the implementation of TDD pursuant to Article 2 does not unduly defer implementation of Decision 2008/477/EC, does not create undue differences in the competitive or regulatory situations between Member States and does not affect the terrestrial systems capable of providing electronic communications services already operating or to be deployed in the 2500-2690 MHz frequency band in accordance with the technical parameters harmonised by Decision 2008/477/EC within other Member States.
- Commission Implementing Decision (EU) 2020/636 of 8 May 2020 amending Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2 500–2 690 MHz frequency band (notified under document C(2020) 2831) (Text with EEA relevance) Decision · Grade B
Commission Decision 2008/477/EC harmonises the technical conditions for using the 2 500–2 690 MHz frequency band (2,6 GHz frequency band) for terrestrial systems capable of providing electronic communications services (ECSs) in the Union, mainly targeting wireless broadband services for end-users.
- Commission Implementing Decision (EU) 2020/636 of 8 May 2020 amending Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2 500–2 690 MHz frequency band (notified under document C(2020) 2831) (Text with EEA relevance) Decision · Grade B
Decision 2008/477/EC should therefore be amended accordingly.
- Commission Implementing Decision (EU) 2020/636 of 8 May 2020 amending Decision 2008/477/EC as regards an update of relevant technical conditions applicable to the 2 500–2 690 MHz frequency band (notified under document C(2020) 2831) (Text with EEA relevance) Decision · Grade B
Decision 2008/477/EC is amended as follows:
- Commission Decision of 31 March 2010 amending Decision 2009/1/EC granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document C(2010) 1987) (Only the Bulgarian text is authentic) (2010/194/EU) Decision · Grade B
Having regard to Commission Decision 2008/477/EC of 13 June 2008 on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community, and in particular Article 2(2) thereof,
- Commission Decision of 31 March 2010 amending Decision 2009/1/EC granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document C(2010) 1987) (Only the Bulgarian text is authentic) (2010/194/EU) Decision · Grade B
By Commission Decision 2009/1/EC, the Republic of Bulgaria has been authorised to postpone the implementation of Decision 2008/477/EC in North Bulgaria until 31 December 2009 and in South Bulgaria until 31 December 2010.
- Commission Decision of 31 March 2010 amending Decision 2009/1/EC granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document C(2010) 1987) (Only the Bulgarian text is authentic) (2010/194/EU) Decision · Grade B
By letter of 25 November 2009, the Republic of Bulgaria therefore requested the extension by one year of the transitional derogation granted by Decision 2009/1/EC. Bulgaria also provided a progress report on the implementation of Decision 2008/477/EC.
- Commission Decision of 31 March 2010 amending Decision 2009/1/EC granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document C(2010) 1987) (Only the Bulgarian text is authentic) (2010/194/EU) Decision · Grade B
The requested extension would not unduly defer implementation of Decision 2008/477/EC nor create undue differences between Member States with respect to competitive or regulatory situations. The request is justified and an extension of the transitional derogation by one year would be appropriate to facilitate the full implementation of Decision 2008/477/EC,
- Commission Decision of 16 December 2008 granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document number C(2008) 8302) (Only the Bulgarian text is authentic) (2009/1/EC) Decision · Grade B
Having regard to Commission Decision 2008/477/EC of 13 June 2008 on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community, and in particular Article 2(2) thereof,
- Commission Decision of 16 December 2008 granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document number C(2008) 8302) (Only the Bulgarian text is authentic) (2009/1/EC) Decision · Grade B
Under Decision 2008/477/EC Member States must designate and subsequently make available, on a non-exclusive basis, the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services subject to specific parameters, within six months of its entry into force.
- Commission Decision of 16 December 2008 granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document number C(2008) 8302) (Only the Bulgarian text is authentic) (2009/1/EC) Decision · Grade B
Member States are required to designate and subsequently make available the 2500-2690 MHz band, in accordance with Decision 2008/477/EC, no later than 13 December 2008.
- Commission Decision of 16 December 2008 granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document number C(2008) 8302) (Only the Bulgarian text is authentic) (2009/1/EC) Decision · Grade B
The Republic of Bulgaria has informed the Commission that, since this band is currently occupied on an exclusive basis by mobile electronic communication equipment used for national security needs, it is not in a position to implement on time the requirements set out in Decision 2008/477/EC.
- Commission Decision of 16 December 2008 granting a derogation requested by the Republic of Bulgaria pursuant to Decision 2008/477/EC on the harmonisation of the 2500-2690 MHz frequency band for terrestrial systems capable of providing electronic communications services in the Community (notified under document number C(2008) 8302) (Only the Bulgarian text is authentic) (2009/1/EC) Decision · Grade B
The requested limitation would not unduly defer implementation of Decision 2008/477/EC nor create undue differences in the competitive or regulatory situations between Member States. The request is justified and a transitional derogation would be appropriate to facilitate the full implementation of Decision 2008/477/EC,